Multiple Choice
The tablet unearthed by the archaeologist revealed an ancient culture's project plan. However, the sands of time had erased much of the information that the table once contained. Use this fragmentary record to unlock the ancient project's secrets and answer the following question(s) .
-Refer to the scenario above. What is the earliest start time for activity H?
A) Week 14
B) Week 15
C) Week 16
D) Week 17
Correct Answer:

Verified
Correct Answer:
Verified