Solved

Bluegrass Builders Ltd Costs incurred to date$925,000\text{Costs incurred to date}\ldots \ldots \ldots \ldots \ldots \ldots \ldots\ldots \ldots \$925,000

Question 9

Multiple Choice

Bluegrass Builders Ltd. Is using the completed-contract method for a $ 2,000,000 contract that will take two years to complete. Data at December 31, 2020, the end of the first year, are Costs incurred to date$925,000\text{Costs incurred to date}\ldots \ldots \ldots \ldots \ldots \ldots \ldots\ldots \ldots \$925,000
Estimated costs to complete1,100,000\text{Estimated costs to complete}\ldots \ldots \ldots \ldots \ldots \ldots \ldots1,100,000
Billings to date850,000\text{Billings to date}\ldots \ldots \ldots \ldots \ldots \ldots\ldots \ldots \ldots \ldots \ldots\ldots 850,000
Collections to date700,000\text{Collections to date}\ldots \ldots \ldots \ldots \ldots \ldots\ldots \ldots \ldots \ldots 700,000
The gross profit or loss that should be recognized for 2020 is


A) $ 50,000 gross profit.
B) $ 25,000 gross profit.
C) $ 25,000 loss.
D) $ 0.

Correct Answer:

verifed

Verified

Unlock this answer now