Essay
Percentage-of-completion and completed-contract methods
On June 15, 2020, Lion Construction signed a $ 360,000 contract to build a small building. Lion estimated that the total cost would be $ 320,000. Construction started immediately because the required completion date was August 31, 2021. Lion’s relevant data relating to this construction project were as follows:
Instructions
Calculate how much gross profit that Lion should recognize each year, assuming:
Method Used For 2020 For 2021
a) Completed contract
b) Percentage-of-completion
Correct Answer:

Verified
Correct Answer:
Verified
Q3: Cost estimates on a long-term contract may
Q4: Concessionary or abnormal terms may<br>A) reflect that
Q5: Timing of revenue recognition/percentage of completion<br>Crush
Q6: Reporting of gross or net revenues<br>Discuss three
Q7: Use the following information for the
Q9: Bluegrass Builders Ltd. Is using the
Q10: The earnings process<br>A) is the same for
Q11: The most popular input measure used to
Q12: According to the AcSB guidelines, the process
Q13: Contract-based approach<br>In January 2020, Bruins Construction