Solved

Use the Information Below to Answer the Following Questions

Question 13

Multiple Choice

Use the information below to answer the following questions:
Multi-Storey Builders Ltd had a large 3-year project with total revenue of $8 000 000 and estimated total costs of $6 500 000. The project was 20% complete at the end of the first year, 70% complete at the end of the second year, and 100% complete at the end of the third year. Revenues and costs were as estimated.
-What profit was earned during the second year if the completed contract method was used?


A) $300 000
B) $750 000
C) $1 050 000
D) $0.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions