On 1 January 2010, Peter Ltd signed a contract worth $64 000 000 to construct the Cycling Stadium. The stadium was to be built over three years, with progress payments as follows:
Estimated costs were $50 000 000. The project was 35% complete at the end of 2010, 75% complete at the end of 2011, and 100% complete at the end of 2012. Revenues and costs were as estimated.
-What profit was earned during 2011 if the percentage of completion method was used?
A) $3 281 250
B) $4 200 000
C) $4 900 000
D) $5 600 000.
Correct Answer:

Verified
Correct Answer:
Verified
Q7: Which of the following statements about the
Q8: Identify the point at which revenue would
Q9: Use the information below to answer
Q10: Use the information below to answer
Q11: Identify the point at which revenue would
Q13: Use the information below to answer the
Q14: Revenue should be recognised when: <br>(i)it can
Q15: Use the information below to answer the
Q16: Identify the point at which revenue would
Q17: Use the information below to answer the