On 1 January 2010, Peter Ltd signed a contract worth $64 000 000 to construct the Cycling Stadium. The stadium was to be built over three years, with progress payments as follows:
$ 31 December 2010 $15000000 31 December 2011 $20000000 31 December 2012 $29000000\begin{array} { r r } & \$ \\\text { 31 December 2010 } & \$ 15000000 \\\text { 31 December 2011 } & \$ 20000000 \\\text { 31 December 2012 } & \$ 29000000\end{array}
Estimated costs were $50 000 000. The project was 35% complete at the end of 2010, 75% complete at the end of 2011, and 100% complete at the end of 2012. Revenues and costs were as estimated.
-What profit was earned during 2011 if the percentage of completion method was used?


A) $3 281 250
B) $4 200 000
C) $4 900 000
D) $5 600 000.