Multiple Choice
Assume that the Assembly Department allocates overhead based on machine hours,and the Finishing Department allocates overhead based on direct labor hours.How much total overhead will be assigned to a product that requires 1 direct labor hour and 2.5 machine hours in the Assembly Department,and 3.5 direct labor hours and 0.5 machine hours in the Finishing Department?
A) $13.00.
B) $10.50.
C) $2.50.
D) $11.00.
E) $7.50.
Correct Answer: