Multiple Choice
In a BIP problem with 3 mutually exclusive alternatives,x1 ,x2 ,and x3,the following constraint needs to be added to the formulation:
A) x1 + x2 +x3 ≤ 1
B) x1 + x2 +x3 = 1
C) x1 - x2 -x3 ≤ 1
D) x1 - x2 -x3 = 1
E) None of the above
Correct Answer:

Verified
Correct Answer:
Verified