Multiple Choice
Refer to the PERT diagram below,where the numbers next to the arrows refer to the number of days required for completion of the corresponding activity.What is the critical path?
A) A-B-D-F
B) A-C-E-F
C) A-B-D-E-F
D) A-C-B-D-F
E) A-C-B-D-E-F
Correct Answer:

Verified
Correct Answer:
Verified