Porter Co Is Analyzing Two Projects for the Future - the Payback Period in Years for Project Y Is

Question 160

Multiple Choice

Porter Co. is analyzing two projects for the future. Assume that only one project can be selected.  Project X  Project Y Cost of machine $68,000$60,000 Net cash flow:  Year 1 24,0004,000 Year 2 24,00026,000 Year 3 24,00026,000 Year 4 020,000\begin{array} { l r r } & \text { Project X } & \text { Project } Y \\\text { Cost of machine } & \$ 68,000 & \$ 60,000 \\\text { Net cash flow: } & & \\\text { Year 1 } & 24,000 & 4,000 \\\text { Year 2 } & 24,000 & 26,000 \\\text { Year 3 } & 24,000 & 26,000 \\\text { Year 4 } & 0 & 20,000\end{array}
- The payback period in years for Project Y is:


A) 2.00.
B) 3.50.
C) 3.20.
D) 3.83.
E) 4.00.

Correct Answer: