A company makes table lamps, for which the following standards have been developed:
During January, production of 100 lamps was expected, but 110 lamps were actually completed.
Direct materials purchased and used were 2,100 kilograms at an actual price of $2.20 per kilogram.
Direct labour cost for the month was $5,310, and the actual pay per hour was $9.00.
-For any actual level of output, the difference between the input that was actually used and the input should have been used is
A) an effectiveness variance.
B) a purchase cost variance.
C) the variance rate.
D) a price variance.
E) an efficiency variance.
Correct Answer:

Verified
Correct Answer:
Verified
Q36: A budget that is adjusted in accordance
Q44: If a purchasing agent is able to
Q45: Use the information below to answer the
Q50: Which of the following reasons is unlikely
Q61: Use the information below to answer the
Q65: Variances and flexible budgets help managers gain
Q110: The flexible-budget variance is the difference between
Q124: The static-budget variance can be subdivided into
Q125: Use the information below to answer the
Q149: Use the information below to answer the