Multiple Choice
Which of the following reasons is unlikely to be related to an unfavourable variance for labour costs?
A) labour used was less skilled than usual
B) poor work scheduling
C) excessive equipment downtime
D) inappropriate standards
E) price variance in direct materials purchased at the standard quality
Correct Answer: