An organisation's accountant is estimating next period's total overhead costs. She performed two regression analyses, one based on direct labor hours and the other based upon machine hours. The results were: Total overhead = $150,000 + $4 x direct labor hours
Adjusted R-square = 0.65
Total overhead = $130,000 + $5 x machine hours
Adjusted R-square = 0.77
For the next period the accountant anticipates using 28,000 direct labor hours and 26,000 machine hours. Based upon this information, what is the best estimate for overhead for the next period?
A) $262,000
B) $260,000
C) $254,000
D) $270,000
Correct Answer:

Verified
Correct Answer:
Verified
Q12: Past cost information, although accurate in predicting
Q38: In a regression equation, variable costs per
Q43: Which graph shows data that are more
Q44: Categorising costs by their behavior is one
Q45: Cost functions are most useful for estimating
Q46: This method of estimating future costs can
Q65: Steel used in the production of automobiles
Q69: Reviewing the pattern of a cost over
Q86: The relevant range is defined as:<br>A) The
Q101: If the organisation has only operated for