Answer the Following Questions Using the Information Below

Question 19

Multiple Choice

Answer the following questions using the information below:
Cycle Safety company is able to produce 1000 safety helmets per hour,at maximum efficiency.There are three eight-hour shifts each day.Due to unavoidable operating interruptions,production averages 850 units per hour.The plant actually operates only 27 days per month.
-What is the practical capacity for the month of April?


A) 720 000 units
B) 1 000 000 units
C) 550 800 units
D) 240 000 units

Correct Answer: