Multiple Choice
Webster Manufacturing Inc. is implementing a Just-in-Time (JIT) system and wants to know how many Kanbans to use for the initial setup of its JIT system. The daily demand is 400 units and each Kanban (i.e., container) holds 15 units. The combined processing and waiting time per container is 0.7 days. If the initial alpha value for safety stock is 0.6, how many Kanban containers should be authorized?
A) More than 10 but less than or equal to 15 Kanbans
B) More than 15 but less than or equal to 20 Kanbans
C) More than 20 but less than or equal to 25 Kanbans
D) More than 25 Kanbans
Correct Answer:

Verified
Correct Answer:
Verified
Q33: In the context of the 5Ss, standardize
Q34: Which of the following Ss of the
Q35: Total productive maintenance (TPM) strives to relieve
Q36: Webster Manufacturing Inc. is implementing a Just-in-Time
Q37: Lean principles are always transferrable to front-office
Q39: Large batches often reduce teardowns and setups
Q40: In a just-in-time (JIT) system, the computer
Q41: Lean principles are mostly beneficial to manufacturers
Q42: _ is NOT a 5S principle that
Q43: Principles of lean operating systems include all