Multiple Choice
Webster Manufacturing Inc. is implementing a Just-in-Time (JIT) system and wants to know how many Kanbans to use for the initial setup of its JIT system. The daily demand is 400 units and each Kanban (i.e., container) holds 15 units. The combined processing and waiting time per container is 0.7 days. If the initial alpha value for safety stock is 0.6, what is the maximum authorized inventory?
A) More than 100 but less than or equal to 200 units
B) More than 200 but less than or equal to 300 units
C) More than 300 but less than or equal to 400 units
D) More than 400 units
Correct Answer:

Verified
Correct Answer:
Verified
Q31: A manufacturer of automobile engines is designing
Q32: Production Kanbans trigger the movement of parts.
Q33: In the context of the 5Ss, standardize
Q34: Which of the following Ss of the
Q35: Total productive maintenance (TPM) strives to relieve
Q37: Lean principles are always transferrable to front-office
Q38: Webster Manufacturing Inc. is implementing a Just-in-Time
Q39: Large batches often reduce teardowns and setups
Q40: In a just-in-time (JIT) system, the computer
Q41: Lean principles are mostly beneficial to manufacturers