The Florida Appliance Company is installing an assembly line to produce vacuum cleaners, and you, as an operations manager, are responsible for balancing the line. The tasks to be performed are listed, along with their times and immediate predecessors. The company is planning to operate 2 shifts per day, 8 hours per shift. The desired output rate of the line is 480 units per day.
a.Compute the cycle time per unit in minutes.
b.Compute the minimum number of workstations required.
c.Use the longest-task-time heuristic to balance the assembly line.
d.Compute the efficiency of your assembly line.
Correct Answer:

Verified
a.Cycle time: CT = A/R = 960/480 = 2 min...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q38: For a given cycle time in line
Q39: A _ layout is an arrangement based
Q40: Steve, an operations manager at Krypto
Q41: Differentiate between a flow-blocking delay and lack-of-work
Q42: Differentiate between product layout, process layout, cellular
Q44: Cellular layouts are designed according to the
Q45: Facility layout is not only concerned with
Q46: Consider the following assembly line information
Q47: All of the following are limitations of
Q48: Workers in cellular layouts generally have greater