John, an operations manager at Clan Corp. must set up an assembly line to assemble a computer mouse. The precedence diagram below is defined with task times in parentheses and stated in minutes. There are 480 minutes of assembly time per shift and there is one shift. The forecast (output rate) is 60 units per shift.
a.Compute the cycle time per unit in minutes.
b.Compute the minimum number of workstations required.
c.Use the longest-task-time heuristic to balance the assembly line.
d.Compute the efficiency of your assembly line.
Correct Answer:

Verified
a.Cycle time = 480/60 = 8 minutes per un...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q59: _ occurs whenever one stage completes work
Q60: An assembly line with 28 activities is
Q61: Assembly-Line Balancing Problem-Table 1 below<br>The Florida
Q62: The typical layout of facilities in a
Q63: The typical layout of facilities in a
Q65: A line-balancing solution has been developed for
Q66: Virtual teams are empowered work teams that
Q67: In designing _ layouts, one is concerned
Q68: An assembly line with 28 activities is
Q69: Discuss four reasons for conducting a facility