Multiple Choice
The bill of material (BOM) for Products A and B are shown below followed by a table of inventory data (called Exhibit 1) . The master production scheduling (MPS) for A calls for 150 units of A to be completed in Week 4 and another 225 units to be completed in Week 5. End item A has a two-week lead time. The MPS calls for 400 units of B to be completed in Week 6. End item B has a one-week lead time. Exhibit 1
____________________________________________________________________
-Using the data given in Exhibit 1, determine the timing and amount of the planned order receipt for Item E.
A) Week 1; 1,800 units
B) Week 3; 1,900 units
C) Week 2; 2,250 units
D) Week 2; 3,850 units
Correct Answer:

Verified
Correct Answer:
Verified
Q55: Given the information below, complete the
Q56: Setting order sizes and schedules for individual
Q57: The master production schedule (MPS) is developed
Q58: A level production strategy maintains constant inventory
Q59: Determine the net requirement for E if
Q61: Work center load reports are used in
Q62: A paint company has the following
Q63: The primary output of a materials requirements
Q64: It is time for a company
Q65: Short-term changes in facilities and equipment are