Multiple Choice
Setting order sizes and schedules for individual subassemblies and resources by week or day fits best with which level of the generic framework for resource planning?
A) Aggregate planning-Level 1
B) Disaggregation-Level 2
C) Execution-Level 3
D) Shop floor controlling-Level 4
Correct Answer:

Verified
Correct Answer:
Verified