Multiple Choice
Which of the following statements is TRUE of the activities not on the critical path?
A) These activities usually cannot be delayed.
B) These activities have less slack than activities on the critical path.
C) These activities can become part of the critical path if delayed long enough.
D) These activities have uncertain times.
Correct Answer:

Verified
Correct Answer:
Verified