The Following Network Shows the Activities on the Circles or Nodes

Question 7

Essay

The following network shows the activities on the circles or nodes. Time estimates are in weeks.  The following network shows the activities on the circles or nodes. Time estimates are in weeks.   Complete the following table:   \begin{array}{|c|l|l|l|l|l|l|l|} \hline\text { Activity } & \text { Time } & \begin{array}{c} \text { Earliest } \\ \text { Start } \end{array} & \begin{array}{c} \text { Earliest } \\ \text { Finish } \end{array} & \begin{array}{c} \text { Latest } \\ \text { Start } \end{array} & \begin{array}{c} \text { Latest } \\ \text { Finish } \end{array} & \text { Slack } & \begin{array}{c} \text { On Critical } \\ \text { Path? } \end{array} \\ \hline \text { A } & & & & & & & \\\hline \mathrm{B} & \\ \hline \mathrm{C} & \\ \hline \mathrm{D} & \\ \hline \mathrm{E} & \\ \hline \mathrm{F} & \\ \hline \end{array} Complete the following table:
 Activity  Time  Earliest  Start  Earliest  Finish  Latest  Start  Latest  Finish  Slack  On Critical  Path?  A BCDEF\begin{array}{|c|l|l|l|l|l|l|l|}\hline\text { Activity } & \text { Time } & \begin{array}{c}\text { Earliest } \\\text { Start }\end{array} & \begin{array}{c}\text { Earliest } \\\text { Finish }\end{array} & \begin{array}{c}\text { Latest } \\\text { Start }\end{array} & \begin{array}{c}\text { Latest } \\\text { Finish }\end{array} & \text { Slack } & \begin{array}{c}\text { On Critical } \\\text { Path? }\end{array} \\\hline \text { A } & & & & & & & \\\hline \mathrm{B} & \\\hline \mathrm{C} & \\\hline \mathrm{D} & \\\hline \mathrm{E} & \\\hline \mathrm{F} & \\\hline\end{array}

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions