Which of the Following Is True of Project Scheduling Using

Question 44

Multiple Choice

Which of the following is true of project scheduling using the critical path method?


A) Activity crash time is greater than normal time.
B) Crash cost per time period is assumed to be non-linear.
C) Gantt charts are built using activity ES, EF, LS, and LF times.
D) Gantt charts assume a beta probability distribution.

Correct Answer: