Which of the following is NOT true of time/cost trade-offs?
A) The relationship between time and cost is proportional and assumed to be linear.
B) Some activities cannot be crashed.
C) Crash time is less than normal time.
D) Crashing priority is based on the amount of uncertainty in activity times.