Multiple Choice
Which one of the following statements about critical path method (CPM) is TRUE?
A) Crashing an activity refers to increasing its normal time.
B) Crashing an activity refers to decreasing its normal time possibly up to its limit.
C) Crashing a project requires revised immediate predecessor relationships.
D) Crashing a project is a tradeoff between revenue and costs.
Correct Answer:

Verified
Correct Answer:
Verified
Q96: List at least six principal factors (contributors)
Q97: Rose is in charge of the
Q98: Define critical path and explain how it
Q99: Crash time is the longest possible time
Q100: Which one of the following is NOT
Q102: Shea is in charge of the
Q103: You are responsible for managing a
Q104: Which of the following terms is least
Q105: Crashing refers to the process of shortening
Q106: You are in charge of the