You are responsible for managing a project with the following activities (times are given in weeks) : Activity A B C D E F G Immediate Predecessor none none none A C A B. D. E. F Normal Time (Weeks) 3625274 Crash Time (Weeks) 2613163 Normal Cost ($) $14,000$5,500$6,000$7,500$9,000$15,000$8,400 Crash Cost ($) $16,500$5,500$8,000$14,500$10,500$18,000$10,000 -What activity should one crash to reduce the project completion time by two weeks at minimum crash costs?
A) A and F. B) A and G. C) A and E. D) G and F.