Question 2

Multiple Choice

You are responsible for managing an advertising project with the following activities (times are given in weeks) .
 Immediate  Normal Time  Crash Time  Normal  Crash  Activity  Predecessor  (Weeks)   (Weeks)   Cost ($)  Cost ($)  A  none 32$14,000$16,500 B  none 66$5,500$5,500 C  none 21$6,000$8,000 D  A, B 53$7,500$14,500 E  C 21$9,000$10,500 F  A 76$15,000$18,000 G  D. E F 43$8,400$10,000\begin{array}{cccccc}&\text { Immediate } & \text { Normal Time } & \text { Crash Time } & \text { Normal } & \text { Crash } \\\text { Activity }&\text { Predecessor } & \text { (Weeks) } & \text { (Weeks) } & \text { Cost }(\$) & \text { Cost }(\$) \\\hline\text { A } & \text { none } & 3 & 2 & \$ 14,000 & \$ 16,500 \\\text { B } & \text { none } & 6 & 6 & \$ 5,500 & \$ 5,500 \\\text { C } & \text { none } & 2 & 1 & \$ 6,000 & \$ 8,000 \\\text { D } & \text { A, B } & 5 & 3 & \$ 7,500 & \$ 14,500 \\\text { E } & \text { C } & 2 & 1 & \$ 9,000 & \$ 10,500 \\\text { F } & \text { A } & 7 & 6 & \$ 15,000 & \$ 18,000 \\\text { G } & \text { D. E F } & 4 & 3 & \$ 8,400 & \$ 10,000\end{array} Draw the project network here. BLANK SPACES
-If activity D is delayed by 2 weeks, which one of the following statements is TRUE?


A) There are now two critical paths in the network.
B) The slack time for activity D changes to 1 week.
C) The project completion time is still 14 weeks.
D) The project completion time becomes 18 weeks.