Multiple Choice
You are responsible for managing an advertising project with the following activities (times are given in weeks) .
Draw the project network here. BLANK SPACES
-If activity D is delayed by 2 weeks, which one of the following statements is TRUE?
A) There are now two critical paths in the network.
B) The slack time for activity D changes to 1 week.
C) The project completion time is still 14 weeks.
D) The project completion time becomes 18 weeks.
Correct Answer:

Verified
Correct Answer:
Verified
Q1: Ayben is responsible for managing an
Q3: Ayben is responsible for managing an
Q4: Ayben is responsible for managing an
Q5: The network below represents a project being
Q6: The early start time for an activity
Q7: The following network shows the activities
Q8: Immediate predecessors are activities that must be
Q9: Rose is in charge of the
Q10: Rose is in charge of the
Q11: You are responsible for managing a