Multiple Choice
Rose is in charge of the advertising program for Proctor & Gamble's new laundry detergent. She has defined the advertising program as a project with the following characteristics. The goal is to complete the project on time and within budget, or she may not have this job next year-the pressure is on!
Draw the project network in the space below if you want. BLANK SPACES
-If activity D is delayed by 2 weeks, the revised earliest project completion time is:
A) 11 weeks.
B) 12 weeks.
C) 13 weeks.
D) 15 weeks.
Correct Answer:

Verified
Correct Answer:
Verified
Q21: You are responsible for managing a
Q55: Activity times are always estimated from historical
Q56: Data regarding the activities for a
Q57: The Baker county government has decided to
Q58: You are responsible for managing a
Q59: Which of the following is NOT considered
Q61: Consider the project network and data
Q62: Explain the stages of the project life
Q64: The critical path method (CPM) work breakdown
Q65: The Critical Path Method (CPM) allows for