You Are Responsible for Managing a Project with the Following
Question 21
Question 21
Multiple Choice
You are responsible for managing a project with the following activities (times are given in weeks) : Activity A B C D E F G Immediate Predecessor none none none A C A B. D. E. F Normal Time (Weeks) 3625274 Crash Time (Weeks) 2613163 Normal Cost ($) $14,000$5,500$6,000$7,500$9,000$15,000$8,400 Crash Cost ($) $16,500$5,500$8,000$14,500$10,500$18,000$10,000 -Which of the following activities has the largest amount of slack?
A) Activity A B) Activity B C) Activity C D) Activity D