Solved

Owens Ltd Produces Specially Machined Parts

Question 13

Multiple Choice

Owens Ltd. produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications) . Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide) and providing space. Costs have been assigned to each activity using direct tracing and resource drivers: Activity cost drivers for each activity have been identified and their practical capacities listed:
Owens Ltd. produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications) . Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide)  and providing space. Costs have been assigned to each activity using direct tracing and resource drivers: Activity cost drivers for each activity have been identified and their practical capacities listed:   The costs of facility-level activities are assigned using machine hours. What is the cost pool rate for the product-level activities?   A)  £80.00 per machine hour B)  £13,500.00 per setup C)  £17.20 per machine hour D)  none of the above The costs of facility-level activities are assigned using machine hours.
What is the cost pool rate for the product-level activities?
Owens Ltd. produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications) . Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide)  and providing space. Costs have been assigned to each activity using direct tracing and resource drivers: Activity cost drivers for each activity have been identified and their practical capacities listed:   The costs of facility-level activities are assigned using machine hours. What is the cost pool rate for the product-level activities?   A)  £80.00 per machine hour B)  £13,500.00 per setup C)  £17.20 per machine hour D)  none of the above


A) £80.00 per machine hour
B) £13,500.00 per setup
C) £17.20 per machine hour
D) none of the above

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions