Answer the following questions using the information below:
Dynondo Incorporated planned to use materials of $12 per unit but actually used materials of $13 per unit, and planned to make 1,500 units but actually made 1,800 units.
-The flexible-budget amount for materials is ________.
A) $18,000
B) $19,500
C) $21,600
D) $23,400