Question 36

Multiple Choice

Answer the following questions using the information below:
Aurous Incorporated planned to use $35 of material per unit but actually used $34 of material per unit, and planned to make 1,500 units but actually made 1,300 units.
-The flexible-budget variance for materials is ________.


A) $1,500 favorable
B) $1,500 unfavorable
C) $1,300 unfavorable
D) $1,300 favorable