The Direct Labour Rate Variance Can Be Expressed As

Question 24

Multiple Choice

The direct labour rate variance can be expressed as:


A) Actual hours x (actual rate - standard rate)
B) Standard rate x (actual hours - standard hours)
C) Actual hours x (standard rate x standard hours)
D) Standard rate x (actual hours/standard hours)

Correct Answer: