menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Successful Project Management Study Set 1
  4. Exam
    Exam 5: Developing the Schedule
  5. Question
    The Latest Finish Time for a Specific Activity Must Be
Solved

The Latest Finish Time for a Specific Activity Must Be

Question 50

Question 50

True/False

The latest finish time for a specific activity must be the same as or earlier than the earliest of all the latest start times of all the activities emerging directly from that specific activity.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q45: Project management is a proactive approach to

Q46: Each activity has two pairs of duration

Q47: The total completion time is 25 days.Task

Q48: In many cases, especially for smaller projects,

Q49: A change in the estimated duration of

Q51: The _ time is the shortest estimated

Q52: Once this baseline plan is agreed upon

Q53: At the beginning of a longer-term project,

Q54: The contractor may not want to commit

Q55: As the project progresses, the actual finish

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines