Multiple Choice
With projects for which there is a high degree of uncertainty about the estimated durations for activities, it is possible to use three time estimates:
A) an original estimate, a petrified estimate, and a most likely estimate.
B) an optimistic estimate, a pessimistic estimate, and a most likely estimate.
C) an optimized estimate, a primary estimate, and a most likely estimate.
D) an opportunity estimate, a pragmatic estimate, and a most likely estimate.
Correct Answer:

Verified
Correct Answer:
Verified
Q9: It is important to know what types
Q10: Throughout the performance of the project, some
Q11: The development team develops, delivers, and demonstrates
Q12: A concentrated effort to accelerate project progress
Q13: The project control process starts with establishing
Q15: Schedule control involves four steps.List the four
Q16: The latest finish time of a specific
Q17: Schedule control involves four steps.Place these steps
Q18: Padding estimates with the vision of becoming
Q19: Earliest finish time (EF)is calculated _.<br>A) by