Multiple Choice
Earliest finish time (EF) is calculated ____.
A) by dividing the activity's latest finish time by the activity's earliest start time.
B) by multiplying the activity's duration estimate with the activity's latest finish time.
C) by adding the activity's duration estimate to the activity's earliest start time.
D) by subtracting the activity's duration estimate from the activity's latest finish time.
Correct Answer:

Verified
Correct Answer:
Verified
Q14: With projects for which there is a
Q15: Schedule control involves four steps.List the four
Q16: The latest finish time of a specific
Q17: Schedule control involves four steps.Place these steps
Q18: Padding estimates with the vision of becoming
Q20: Eliminating negative slack by reducing durations of
Q21: Calculate the earliest finish for Task D
Q22: The estimated duration for each activity must
Q23: The duration of a task is<br>A) the
Q24: The latest start time for a specific