Multiple Choice
Given this project and the requirement that the number of resources working on a task cannot be less than the number assigned to the task, answer the following question.What is the least number of resources that can be assigned to the project if all five tasks occur in parallel?
A) 24 workers
B) 1.5 workers per day
C) 7 workers
D) 2 workers
Correct Answer:

Verified
Correct Answer:
Verified
Q15: If resources are to be considered in
Q18: This example has level resources of three
Q27: Resource-limited scheduling will not extend the project
Q29: The start of noncritical activities are delayed
Q31: When several activities need the same limited
Q36: In addition to showing the technical constraints
Q37: Why are activities drawn in a serial
Q39: In resource-limited scheduling, the lower priority activities
Q41: Activities can be delayed only to the
Q45: Resource utilization charts based on each activity's