Multiple Choice
This example has level resources of three resources for eight days.If the project is limited to two resources, how should the project be organized to meet the resource constraint and finish the project as early as possible? The tasks with the least slack have the lower number.
A) Paths would be 1,2,3,5 and 1,2,4
B) Paths would be 1,2,3,4 and 1,2,5
C) Paths would be 1,2 and 3,4,5
D) Path would be 1,2,3,4,5
Correct Answer:

Verified
Correct Answer:
Verified
Q15: If resources are to be considered in
Q21: Given this project and the requirement that
Q27: Resource-limited scheduling will not extend the project
Q29: The start of noncritical activities are delayed
Q31: When several activities need the same limited
Q36: In addition to showing the technical constraints
Q37: Why are activities drawn in a serial
Q39: In resource-limited scheduling, the lower priority activities
Q41: Activities can be delayed only to the
Q45: Resource utilization charts based on each activity's