Multiple Choice
Some level of risk planning should be done during ____ of the project life cycle to make sure that a contractor understands the risks involved with bidding on a proposed project.With knowledge of potential risks, the contractor can include contingency or management reserve amounts in the bid price.
A) the planning phase
B) the performing phase
C) the initiating phase
D) the closing phase
Correct Answer:

Verified
Correct Answer:
Verified