Essay
A manufacturing company is interested in making a product structure tree for one of its major products.They know that product A is made up of assemblies B, C, and D.Each B assembly is made up of one raw material F, and 2 E parts.Each C assembly is composed of 2 G parts and one H subassembly.Each H sub?assembly is made up of 2 F raw materials, 2 1 parts and 2 J parts.
a.How many units of part G are needed to make one unit of product A?
b.How many units of raw material F are needed to make up one unit of product A?
Correct Answer:

Verified
Correct Answer:
Verified
Q1: A cement company is considering how to
Q3: Promotion of weekly discount airfares by an
Q4: If forecast demand exceeds the total factory
Q5: Assigning people to tasks, setting priorities for
Q6: A sheet metal company has developed the
Q7: Service firms frequently take their aggregate plans
Q8: The BOM for Product X is shown
Q9: Which lot sizing rule might use the
Q87: Aggregate planning and disaggregation methods in goods-producing
Q102: Describe the options that managers have for