A Sheet Metal Company Has Developed the Following Six-Month Production

Question 6

Essay

A sheet metal company has developed the following six-month production schedule (in thousands of square yards):
A sheet metal company has developed the following six-month production schedule (in thousands of square yards):    In addition, their monthly labor and machine capacities (in hours) available, and the production standards (in hours per square yard) are:    a.What is the percent utilization of the labor capacity in month 4? b.What is the percent utilization of the machine capacity in month 3? c.In how many weeks are the labor requirements over capacity? In addition, their monthly labor and machine capacities (in hours) available, and the production standards (in hours per square yard) are:
A sheet metal company has developed the following six-month production schedule (in thousands of square yards):    In addition, their monthly labor and machine capacities (in hours) available, and the production standards (in hours per square yard) are:    a.What is the percent utilization of the labor capacity in month 4? b.What is the percent utilization of the machine capacity in month 3? c.In how many weeks are the labor requirements over capacity?
a.What is the percent utilization of the labor capacity in month 4?
b.What is the percent utilization of the machine capacity in month 3?
c.In how many weeks are the labor requirements over capacity?

Correct Answer:

verifed

Verified

a.Labor utilization:
Required capacity =...