The Eugene plant of Basic Computers Inc.(BCI) wants to develop a net requirements schedule for one model of microcomputers.The beginning inventory is 500 units and they like to carry 50 units as safety stock.The estimated demand for the next 6 weeks is 200, 250, 300, 375, 400, and 600 units.
a.What would the net requirements be for week 3?
b.What is the beginning inventory in week 5?

Correct Answer: