Essay
A special project in a manufacturing company has the following master production schedule (MPS) for the next eight weeks:
The weekly fabrication and welding capacity (in hours) available and production standards (in hours per unit) are:
a.What is the percent utilization of the fabrication capacity in week 5?
b.What is the percent utilization of the welding capacity in week 2?
c.In how many weeks are the welding area requirements over capacity?
Correct Answer:

Verified
a.Fabrication utilization:
Required capa...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
Required capa...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q9: Explain the three levels of resource planning.
Q29: A company currently has no items in
Q43: The purpose of the master schedule is
Q46: Setting order sizes and schedules for individual
Q48: The bill of material for end item
Q50: A firm produces one product on a
Q54: A POQ for a one-week time period
Q55: The Eugene plant of Basic Computers Inc.(BCI)
Q56: Explain a bill of materials (BOM), bill
Q67: Dependent demand does not occur in the