Multiple Choice
A requirement of Johnson's two-resource sequencing rule is
A) All jobs must begin at the same time
B) Jobs must be processed through each work center in the same job sequence
C) Only two jobs can be processed at a time through each work center
D) Total processing time must be minimized
Correct Answer:

Verified
Correct Answer:
Verified