A print shop has four jobs that have to be processed through their only five-color press.They usually use the first-come first-served method of scheduling jobs.However, the customers are waiting in the lobby for these jobs so the shop wants to minimize the average waiting time.They are going to use the shortest processing time rule to do so.Processing times for each job are as follows (assume this is the arrival order): Job A, 30 minutes; Job B, 17 minutes; Job C, 12 minutes; Job D, 39 minutes.
a.In what order should the four jobs be done using the shortest processing time rule?
b.What is the average waiting (flow) time for all jobs using the shortest processing time rule?
c.What is the averaging waiting (flow) time using their usual first-come first-served rule?
Correct Answer:

Verified
a.Shortest processing time:
Order of job...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
Order of job...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q1: The following five jobs, along with their
Q2: A movie theater requires the following minimum
Q3: In practice, whenever processing times of a
Q5: If the highest priority is to minimize
Q7: Two examples of process-focused performance measures for
Q8: A requirement of Johnson's two-resource sequencing rule
Q10: A new surgical facility called Cut &
Q11: The shortest processing time rule and earliest
Q19: Scheduling refers to determining the order in
Q46: Sequencing is not as much of a