Essay
A company is using a Kanban system with 2 containers, each holding 50 parts, between a downstream (using) and an upstream (producing) work center.The using work center can handle 250 jobs per day.The average elapsed time for the entire cycle is currently .25 days.The company is concerned with the safety factor for the operation and the size of the containers.
a.What is the efficiency rating of the current operation?
b.If the company decides to use only one container, how many parts must it hold?
c.If the safety factor is changed to .12 and there are still 2 containers, how many parts must each container now hold?
Correct Answer:

Verified
a.
= [KC - d(p + w)] / d(p + w) = [(2)(5...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q21: A manufacturing company is using a two-container
Q23: Ford Motor Company has decided to switch
Q25: Total Production Maintenance (TPM)<br>A)Puts total responsibility on
Q27: Compare and contrast a push system vs.a
Q28: Firms use the "5S" principles to create
Q29: A company is using Kanban containers.There
Q30: The number of Kanban cards is directly
Q31: Which of the following is not one
Q54: Lean production is focused on efficiency by
Q77: A clean and organized work area is