A manufacturing company is planning to use PERT to setup a project for a new production line.For this project, they have established the following activities, precedence relationships, and time estimates in days:
a.What is the expected duration for activity b?
b.What is the variance of activity d?
c.How many paths are there in the network?
d.What is the earliest finish (EF) time for activity e?
e.What is the slack in days for activity c?
f.What is the critical path?
g.What is the duration of the critical path in days?
h.What is the standard deviation of the critical path?
i.What is the probability of completing the project within 50 days?
Correct Answer:

Verified
a. te = (to + 4tView Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q6: The early start time for an activity
Q8: Immediate predecessors are activities that must be
Q23: The critical path is the sequence of
Q46: Which of the following is not considered
Q47: Project management objectives revolved around on-time and
Q49: You are in charge of the "advertising
Q52: Because the preparation of annual reports is
Q53: In which stage in the project life
Q55: In which stage in the project life
Q56: Which of the following is incorrect regarding