Essay
You are in charge of the "advertising program" for the Boston Red Sox baseball team during their spring training in Fort Myers, Florida.You have defined the advertising program as a project with the following characteristics.The goal is to fill all stadium seats during the spring training season.
a.What is the earliest completion time for this project?
b.What is the largest amount of slack that any activity has in this project?
c.If activity C is delayed three weeks, what is the revised earliest project completion time?
d.For the original CPM problem, what is the minimum number of activities that would have to be crashed in order to reduce the project's earliest completion time by two weeks assuming all activity crash costs per week are the same and all activities can be crashed?
Correct Answer:

Verified
a.12 weeks...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q6: The early start time for an activity
Q8: Immediate predecessors are activities that must be
Q23: The critical path is the sequence of
Q43: All activities on the critical path have
Q46: Which of the following is not considered
Q47: Project management objectives revolved around on-time and
Q51: A manufacturing company is planning to use
Q52: Because the preparation of annual reports is
Q53: In which stage in the project life
Q68: Using a beta probability distribution to characterize