A company has a PERT project with path b-d-e-g-i that has these activity time estimates in days:
A company has a PERT project with path b-d-e-g-i that has these activity time estimates in days:    a.What is the expected duration for activity  e ? b.What is the variance for activity  b ? c.What is the standard deviation of the path?
a.What is the expected duration for activity "e"?
b.What is the variance for activity "b"?
c.What is the standard deviation of the path?

Correct Answer:

verifed

Verified

a.te = (to + 4t