A company has used PERT for a project and wants to minimize the probability of overrunning a contract deadline of 30 weeks.Three paths of concern in the PERT network have these mean durations and variances in weeks:
A company has used PERT for a project and wants to minimize the probability of overrunning a contract deadline of 30 weeks.Three paths of concern in the PERT network have these mean durations and variances in weeks:     a.What is the Z-score for path 1? b.What is the probability of path 2 overrunning the deadline?
a.What is the Z-score for path 1?
b.What is the probability of path 2 overrunning the deadline?

Correct Answer:

verifed

Verified

a.Z = (T - D)/Std.dev.of path
Path 1: Z ...