Multiple Choice
If Activity C directly precedes both D and E on a project network and C can be crashed three (3) times in using linear programming,
A) Crash time affects only C
B) Crash time affects only C and D
C) Crash time affects only C and E
D) Crash time affects both D and E
Correct Answer:

Verified
Correct Answer:
Verified
Q1: A Singapore company manufactures 50-inch and 75-inch
Q2: A computer manufacturing company wants to develop
Q5: The constraint that requires the beginning inventory
Q6: If R<sub>m</sub> = increase in the total
Q7: <span class="ql-formula" data-value="\sqrt{x}"><span class="katex"><span class="katex-mathml"><math xmlns="http://www.w3.org/1998/Math/MathML"><semantics><mrow><msqrt><mi>x</mi></msqrt></mrow><annotation encoding="application/x-tex">\sqrt{x}</annotation></semantics></math></span><span
Q8: The normal-time project cost does not depend
Q9: A cement company has three factories that
Q10: If for a given month overtime units
Q11: The Pacific Computer Company makes two models
Q27: For linear programming to work for project